Professional framing for a 1-3 bedroom unit typically takes 3-7 days. Timeline depends on layout complexity, material availability, and inspections. Custom designs or delays in lumber delivery may extend this. The site must have completed foundation work and passed initial inspections. For your exact timeframe, we recommend an on-site estimate to assess your specific project requirements and potential variables.
Professional drywall for a 1-3 bedroom unit typically takes 4-9 days (hanging: 1-4 days, taping/mudding: 3-5 days with drying time). Factors affecting schedule: Ceiling height/textures Room complexity (angles, bulkheads) Drywall type (standard vs. fire/soundproof) Climate (humidity affects drying) Final timing confirmed during on-site assessment.
Professional Taping/Mudding for a 1-3 bedroom unit typically takes 4-9 days drying time. Factors affecting schedule: Ceiling height/textures Room complexity (angles, bulkheads) Final timing confirmed during on-site assessment.
Transform your unused basement into beautiful, functional living space with our streamlined development process. From initial design to the final finishing touches, a typical full basement development is a carefully managed project we complete in approximately 4 to 8 weeks. This comprehensive timeline includes everything from framing and insulation to electrical, plumbing, drywall, and flooring, ensuring a high-quality result without unnecessary delays. Let us guide you through a seamless renova
We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.